Project

A project is an endeavour that aims to achieve specific goals within a fixed period of time under certain resource constraints. They are unique, temporary, and constrained.

Quality of a project is generally constrained by scope, cost, and time. Adjusting one but not the other may cause quality to suffer.

Link to original

Project Manager

Roles of a project manager:

  • Proposal writing.
  • Reporting.
  • Project planning and scheduling: deciding tasks, estimating costs, scheduling tasks, allocating people and resources to tasks.
  • Risk management: identity, assess, monitor and address risks.
  • People management: choose people and establish ways of working.
Link to original

Project Planning

Project Planning

Link to original

Task (Project Planning)

Tasks are the basic unit of scheduling, they posses:

  • A description of the task.
  • The “effort” / number of work units a task requires.
  • Duration of the task / amount of time taken to complete a task.
  • Elapsed time / amount of time between start and end of a task.
  • Deadline which is the time the task needs to be complete by.
  • Dependencies that other project activities this activity depends on.
  • Prerequisites which are required before starting this task.
  • Defined endpoint which is a clearly specified condition which indicates the end of the activity.
Link to original

Milestone (Project Planning)

A milestone is the end of a “project stage”:

  • Correspond to completion of a set of activities.
  • Reaching a milestone usually involves a report.
  • Milestones are not deliverables.
Link to original

Gantt Chart

A Gantt chart visually represents time allocations for tasks and milestones.

Link to original

Risk Management

Risk Management

An example risk management process:

  • Risk identification: list potential risks Estimation risks, organisation risks, people risks, requirements risks, technology risks, tools risks.
  • Risk analysis: prioritised list of risks
    • Probability of risk: qualitative label assessing the likeliness of something happening; insignificant, low, moderate, high, very high.
    • Effect of risk: qualitative label assessing impact; insignificant, tolerable, serious, catastrophic.
  • Risk planning: risk avoidance & contingency plans
    • Risk acceptance: no action.
    • Risk prevention: upfront action to stop risk arising.
    • Risk reduction: upfront action to reduce probability / impact of risk.
    • Risk transfer: transfer risk to someone else.
    • Contingency planning: no upfront action, plan response in case risk arises.
  • Risk monitoring: risk assessment
Link to original